Karbi Anglong 1,300 MW Power Project: 190.7 Hectares of Forest Land Explained

Karbi Anglong 1,300 MW Power Project: 190.7 Hectares of Forest Land Explained

A proposed 1,300 MW pumped-storage power project in West Karbi Anglong, Assam, has drawn attention after a forest advisory panel reportedly recommended in-principle approval for the diversion of 190.7 hectares of forest land.

The proposed project, identified as Assam PSP-05 in the Central Electricity Authority's hydro development profile, is part of Assam's expanding pumped-storage energy plans.

According to a report published by The Sentinel on November 25, 2026, the Ministry of Environment, Forest and Climate Change (MoEFCC) Advisory Committee recommended Stage-I approval for the proposed forest land diversion, subject to environmental and other conditions.

The proposal has raised important questions about forest conservation, wildlife protection, local natural resources and the long-term impact of large infrastructure development in the Karbi Anglong hills.

Here is what is currently known about the project, the forest clearance process and its potential implications.

What Is the Karbi Anglong 1,300 MW Power Project?

The project is a proposed off-stream closed-loop pumped-storage hydroelectric energy storage facility in West Karbi Anglong district, Assam.

The Central Electricity Authority (CEA), in its hydro development profile dated November 11, 2026, lists Assam PSP-05 as a 1,300 MW pumped-storage project in West Karbi Anglong.

The CEA's project table identifies Hinduja Renewables Energy Pvt. Ltd. as the agency associated with Assam PSP-05 and lists the project under the survey and investigation category.

Separately, The Sentinel's November 25 report identifies Assam Power Distribution Company Limited (APDCL) as the forest-diversion proposal proponent.

The precise relationship between the project developer and the forest-diversion applicant should be confirmed through the relevant PARIVESH project record.

Unlike conventional hydropower projects that generate electricity through continuous river flow, a pumped-storage project primarily stores electricity for later use.

It uses electricity during periods of lower demand to pump water from a lower reservoir to an upper reservoir. During peak electricity demand, the stored water is released through turbines to generate electricity.

This system can help balance electricity supply and demand and support the integration of solar and wind energy.

190.7 Hectares of Forest Land Proposed for Diversion

According to The Sentinel's November 25, 2026 report, the project requires the diversion of approximately 190.7 hectares of forest land in the Hamren Forest Division of West Karbi Anglong.

The report provides the following forest classification:

Forest classificationArea
Very dense forest3.27 hectares
Moderately dense forest94.07 hectares
Open forest64.41 hectares
Total proposed forest diversion190.7 hectares

The published classification figures add up to 161.75 hectares, leaving 28.95 hectares without a classification breakdown in the report. The complete official forest proposal should be consulted for the remaining details.

The proposed diversion is significant because forest land provides ecological services such as soil protection, water retention, carbon storage and wildlife habitat.

Any large-scale conversion of forest land therefore requires careful assessment and appropriate safeguards.

3,940 Trees and 2,66,300 Bamboo Poles May Be Affected

One of the most significant details in the November 25 report concerns vegetation removal.

According to the report, the proposed project may require:

  • Felling of approximately 3,940 trees.

  • Removal of approximately 2,66,300 bamboo poles.

  • Impact on bamboo belonging to around 50 different species.

These figures are reported estimates associated with the proposed forest diversion. They should not be interpreted as confirmation that tree felling has already taken place.

The final extent of vegetation removal will depend on the approved project layout, applicable clearances and compliance with the prescribed conditions.

Why Has the Forest Advisory Committee Recommended In-Principle Approval?

The Advisory Committee of the Ministry of Environment, Forest and Climate Change reportedly examined the proposal at a recent meeting in New Delhi.

According to The Sentinel, the committee considered the project's potential contribution to renewable-energy integration, reduced dependence on conventional energy sources and regional socio-economic development.

The committee recommended Stage-I or in-principle approval under the Van (Sanrakshan Evam Samvardhan) Adhiniyam, 1980, subject to several conditions.

However, a recommendation for in-principle approval should not be confused with final forest clearance.

The project must meet the applicable conditions and obtain the necessary subsequent approvals before the forest land can be handed over for the approved non-forest use.

Environmental Conditions Attached to the Reported Forest Approval

The November 25 report identifies several important environmental safeguards.

1. Site-Specific Wildlife Management Plan

The Assam Government is required to prepare a site-specific Wildlife Management Plan in consultation with the Chief Wildlife Warden.

The plan is expected to include measures for wildlife conservation and habitat protection in and around the proposed project area.

The completed plan must be submitted to the MoEFCC along with the relevant compliance report.

2. Catchment Area Treatment Plan

A Catchment Area Treatment (CAT) Plan must also be prepared for the project's catchment area.

The plan is intended to address environmental problems such as soil erosion, land degradation and impacts on the surrounding catchment.

According to the report, APDCL will bear the cost of implementing the plan, with funds deposited into the designated CAMPA account through the PARIVESH payment system.

3. Soil and Moisture Conservation Measures

The proposed project area is reported to be vulnerable to soil erosion.

A Soil and Moisture Conservation Plan approved by the competent authority will therefore be required.

The project proponent must implement the approved measures at its own cost.

4. Water Management and Reservoir Filling

The reported conditions also address water availability.

For the initial filling of the reservoirs, water is to be drawn during the monsoon season, when river flow is at its maximum.

The project proponent must also implement appropriate measures for:

  • Water conservation.

  • Rainwater harvesting.

  • Groundwater recharge.

  • Improved local water retention.

  • Reducing pressure on existing water sources during the lean season.

These safeguards are particularly relevant in areas where seasonal water availability can affect local communities and ecosystems.

5. Dam Safety and Muck Disposal

The project must follow the approved dam design and applicable dam safety standards during construction and after construction.

The proposed muck-dumping locations must also be restored using suitable biological and engineering measures after dumping activities are completed.

These conditions are intended to reduce construction-related environmental damage.

What Does Stage-I Forest Clearance Mean?

The difference between Stage-I and Stage-II forest clearance is important for understanding this development.

Under India's forest conservation framework, diversion of forest land for non-forest purposes requires prior Central Government approval under the Van (Sanrakshan Evam Samvardhan) Adhiniyam, 1980.

Stage-I: In-Principle Approval

Stage-I approval indicates that the proposal has received conditional acceptance.

The project authorities must fulfil the prescribed conditions, which may include:

  • Payment of Net Present Value (NPV).

  • Compensatory afforestation requirements.

  • Wildlife conservation measures.

  • Catchment area treatment.

  • Soil and moisture conservation.

  • Other project-specific environmental safeguards.

Stage-II: Final Forest Clearance

After the required conditions have been fulfilled and compliance has been examined, the Central Government may grant final approval.

The forest land can then be handed over for the approved non-forest purpose in accordance with the applicable requirements.

Important: As of November 25, 2026, the available reporting establishes a Stage-I recommendation for the 1,300 MW proposal, not confirmation of final Stage-II clearance.

Therefore, it would be incorrect to report that the project has already received unrestricted permission to begin construction on the proposed forest land.

Why Is the Project Important for Assam?

Assam's electricity requirements are expected to grow alongside industrial development, urbanisation and increasing demand for reliable power.

Pumped-storage facilities can help address fluctuations in electricity demand by storing energy when demand is low and supplying electricity during peak periods.

The proposed 1,300 MW project could potentially contribute to:

  1. Energy storage capacity for Assam.

  2. Better integration of renewable energy.

  3. Electricity supply during peak demand.

  4. Greater flexibility in power-system operations.

  5. Infrastructure development in West Karbi Anglong.

However, the project's actual contribution will depend on its technical feasibility, environmental clearances, financing, construction and eventual commissioning.

A proposed installed capacity of 1,300 MW does not mean the facility is already generating electricity.

Environmental and Community Concerns

While pumped-storage infrastructure can support energy security, forest diversion on this scale raises legitimate environmental and social questions.

The reported vegetation impact, particularly the proposed removal of thousands of trees and hundreds of thousands of bamboo poles, requires careful scrutiny.

Important issues that deserve public attention include:

  • Potential loss of forest habitat.

  • Effects on wildlife movement and biodiversity.

  • Soil erosion and changes in local drainage.

  • Water availability during dry periods.

  • Impacts on agricultural and forest-dependent livelihoods.

  • Land rights and the interests of indigenous communities.

  • Transparency in environmental assessment and compliance monitoring.

The existence of these potential concerns does not establish that specific communities will be displaced or that particular wildlife populations will be harmed.

Such conclusions require project-specific environmental assessments, land records, public consultation documents and official impact studies.

Local residents and affected stakeholders should have access to relevant project documents and opportunities to raise concerns through the applicable legal and environmental processes.

Is the Karbi Anglong Power Project the Same as the 900 MW Tharakunchi Project?

No. Readers should not confuse the 1,300 MW Assam PSP-05 proposal with the separate 900 MW Assam PSP-01 project near Tharakunchi.

The CEA's November 11, 2026 profile lists these as separate projects.

The 900 MW Assam PSP-01 project is associated with Greenko Assam-01 and APDCL's project nomenclature. The CEA profile records that Stage-I forest clearance was obtained on February 13, 2026, with Stage-I compliance under progress for Stage-II clearance.

The 1,300 MW Assam PSP-05 is separately listed under Hinduja Renewables Energy Pvt. Ltd. and the survey and investigation category.

The two projects have different capacities and should be reported separately.

What Happens Next?

The next important developments will concern compliance with the reported Stage-I conditions and the project's remaining approval requirements.

Readers should watch for:

  1. Publication of the official Stage-I forest approval order.

  2. Submission of the Wildlife Management Plan.

  3. Approval and implementation of the Catchment Area Treatment Plan.

  4. Compliance with soil and moisture conservation requirements.

  5. Details of compensatory afforestation and other applicable payments.

  6. Further environmental and technical appraisal.

  7. Clarification of the project developer and forest-diversion applicant.

  8. Any official updates on final Stage-II forest clearance.

The status of the project should be checked against the latest government records before publishing any claim about construction commencement or final approval.

Frequently Asked Questions (FAQs)

1. What is the Karbi Anglong 1,300 MW power project?

It is a proposed off-stream closed-loop pumped-storage hydroelectric energy storage project in West Karbi Anglong, Assam, listed as Assam PSP-05 in the Central Electricity Authority's project profile.

2. How much forest land is proposed for diversion?

According to The Sentinel's November 25, 2026 report, approximately 190.7 hectares of forest land in the Hamren Forest Division is proposed for diversion.

3. Has the 1,300 MW Karbi Anglong project received final forest clearance?

Final Stage-II clearance has not been established by the available evidence. The November 25 report describes a Stage-I or in-principle recommendation subject to conditions.

4. How many trees may be affected by the project?

The November 25 report estimates that approximately 3,940 trees and 2,66,300 bamboo poles may be affected by the proposed forest diversion.

5. What is a pumped-storage power project?

A pumped-storage project stores electricity by pumping water from a lower reservoir to an upper reservoir during periods of lower demand. Water is later released through turbines to generate electricity during peak demand.

6. Who is developing the Assam PSP-05 project?

The CEA's November 11, 2026 profile identifies Hinduja Renewables Energy Pvt. Ltd. as the agency associated with Assam PSP-05. The Sentinel's November 25 report identifies APDCL as the forest-diversion proponent. The precise project and applicant relationship requires confirmation from the official PARIVESH record.

7. What environmental conditions have been reported?

The reported conditions include a Wildlife Management Plan, Catchment Area Treatment Plan, Soil and Moisture Conservation Plan, water conservation measures, dam safety compliance and restoration of muck-dumping locations.

8. Is the 1,300 MW project the same as the 900 MW Tharakunchi project?

No. They are separate pumped-storage proposals with different capacities and project records.

Conclusion

The proposed 1,300 MW Karbi Anglong Power Project represents an important development in Assam's energy-storage plans, but the reported diversion of 190.7 hectares of forest land has also brought environmental protection into focus.

The reported Stage-I recommendation includes several safeguards relating to wildlife, catchment management, water conservation, soil protection and dam safety.

The next stage will be crucial in determining whether the project can fulfil the necessary conditions and obtain the remaining approvals.

For residents of West Karbi Anglong and people across Assam, transparency, environmental accountability and protection of local natural resources will remain essential as the project progresses.

InsideStoryToday.in will continue tracking official clearance documents, environmental developments and updates concerning the proposed Karbi Anglong power project.


Sources and References

  1. The Sentinel – Assam Govt Approves Forest Land Diversion for Power Plant Amid Environmental Concerns (November 25, 2026).

  2. Central Electricity Authority – State Profile on Hydro Development for Assam (November 11, 2026).

  3. Ministry of Environment, Forest and Climate Change – Annual Report 2025–26, Forest Conservation chapter.

  4. PARIVESH – Government of India's environmental and forest clearance portal.

Editorial clarification: The 190.7-hectare diversion, tree and bamboo estimates and Stage-I recommendation are attributed to The Sentinel's reporting. The CEA independently lists the 1,300 MW Assam PSP-05 proposal but does not establish final forest clearance. No claim of final Stage-II approval or completed construction is made in this article.